NESHAP Subpart JJJJJJ (Area source boiler rule): Industrial, Commercial, and Institutional Boilers Area Sources

Subpart JJJJJJ—National Emission Standards for Hazardous Air Pollutants for Industrial, Commercial, and Institutional Boilers Area Sources
Rule text from eCFRLast amended in eCFR 2018-07-02

Where this text comes from

Citation
40 CFR Part 63, Subpart JJJJJJ
Official title
Subpart JJJJJJ—National Emission Standards for Hazardous Air Pollutants for Industrial, Commercial, and Institutional Boilers Area Sources
Text as of
eCFR current through 2026-10-28, retrieved 2026-10-30
Latest amendment
2018-07-02
Source note
76 FR 15591, Mar. 21, 2011, unless otherwise noted.

Headings and quoted sections on this page are copied from the eCFR text of Subpart JJJJJJ without changes. AirPermitHub checks eCFR every week and reviews any change before publishing it, so this page can trail eCFR by a few days. eCFR is maintained by the Office of the Federal Register and the Government Publishing Office. It is not an official legal edition of the CFR, and it does not show how an agency has applied the rule in a permit.

Where to look in Subpart JJJJJJ

Sections sorted by the words in their eCFR headings. Read the full section before relying on it; requirements often sit in more than one place.

Compliance dates
§ 63.11210
Tests, methods, and calculations
§ 63.11212§ 63.11213§ 63.11220
Notifications, reports, records
§ 63.11225
Definitions
§ 63.11237
Who implements it
§ 63.11236
General provisions
§ 63.11235

Who the subpart covers, in the rule's own words

The sections that set out what the subpart applies to, quoted in full from eCFR. Dates, sizes, and other figures are the rule's, not AirPermitHub's.

§ 63.11193 Am I subject to this subpart?

Open in eCFR

You are subject to this subpart if you own or operate an industrial, commercial, or institutional boiler as defined in § 63.11237 that is located at, or is part of, an area source of hazardous air pollutants (HAP), as defined in § 63.2, except as specified in § 63.11195.

§ 63.11194 What is the affected source of this subpart?

Open in eCFR

(a) This subpart applies to each new, reconstructed, or existing affected source as defined in paragraphs (a)(1) and (2) of this section.

(1) The affected source of this subpart is the collection of all existing industrial, commercial, and institutional boilers within a subcategory, as listed in § 63.11200 and defined in § 63.11237, located at an area source.

(2) The affected source of this subpart is each new or reconstructed industrial, commercial, or institutional boiler within a subcategory, as listed in § 63.11200 and as defined in § 63.11237, located at an area source.

(b) An affected source is an existing source if you commenced construction or reconstruction of the affected source on or before June 4, 2010.

(c) An affected source is a new source if you commenced construction of the affected source after June 4, 2010, and the boiler meets the applicability criteria at the time you commence construction.

(d) An affected source is a reconstructed source if the boiler meets the reconstruction criteria as defined in § 63.2, you commenced reconstruction after June 4, 2010, and the boiler meets the applicability criteria at the time you commence reconstruction.

(e) An existing dual-fuel fired boiler meeting the definition of gas-fired boiler, as defined in § 63.11237, that meets the applicability requirements of this subpart after June 4, 2010 due to a fuel switch from gaseous fuel to solid fossil fuel, biomass, or liquid fuel is considered to be an existing source under this subpart as long as the boiler was designed to accommodate the alternate fuel.

(f) If you are an owner or operator of an area source subject to this subpart, you are exempt from the obligation to obtain a permit under 40 CFR part 70 or part 71 as a result of this subpart. You may, however, be required to obtain a title V permit due to another reason or reasons. See 40 CFR 70.3(a) and (b) or 71.3(a) and (b). Notwithstanding the exemption from title V permitting for area sources under this subpart, you must continue to comply with the provisions of this subpart.

[76 FR 15591, Mar. 21, 2011, as amended at 78 FR 7506, Feb. 1, 2013]

Every section in Subpart JJJJJJ

21 sections and 8 tables, in eCFR order. Each link opens the official text.

What This Subpart Covers

  • § 63.11193Am I subject to this subpart?Amended 2016-12-22
  • § 63.11194What is the affected source of this subpart?Amended 2016-12-22
  • § 63.11195Are any boilers not subject to this subpart?Amended 2016-12-22
  • § 63.11196What are my compliance dates?Amended 2016-12-22

Emission Limits, Work Practice Standards, Emission Reduction Measures, and Management Practices

  • § 63.11200What are the subcategories of boilers?Amended 2016-12-22
  • § 63.11201What standards must I meet?Amended 2016-12-22

General Compliance Requirements

  • § 63.11205What are my general requirements for complying with this subpart?Amended 2016-12-22

Initial Compliance Requirements

  • § 63.11210What are my initial compliance requirements and by what date must I conduct them?Amended 2016-12-22
  • § 63.11211How do I demonstrate initial compliance with the emission limits?Amended 2016-12-22
  • § 63.11212What stack tests and procedures must I use for the performance tests?Amended 2016-12-22
  • § 63.11213What fuel analyses and procedures must I use for the performance tests?Amended 2016-12-22
  • § 63.11214How do I demonstrate initial compliance with the work practice standard, emission reduction measures, and management practice?Amended 2016-12-22

Continuous Compliance Requirements

  • § 63.11220When must I conduct subsequent performance tests or fuel analyses?Amended 2016-12-22
  • § 63.11221Is there a minimum amount of monitoring data I must obtain?Amended 2016-12-22
  • § 63.11222How do I demonstrate continuous compliance with the emission limits?Amended 2016-12-22
  • § 63.11223How do I demonstrate continuous compliance with the work practice and management practice standards?Amended 2016-12-22
  • § 63.11224What are my monitoring, installation, operation, and maintenance requirements?Amended 2016-12-22
  • § 63.11225What are my notification, reporting, and recordkeeping requirements?Amended 2016-12-22
  • § 63.11226[Reserved]Amended 2016-12-22

Other Requirements and Information

  • § 63.11235What parts of the General Provisions apply to me?Amended 2016-12-22
  • § 63.11236Who implements and enforces this subpart?Amended 2016-12-22
  • § 63.11237What definitions apply to this subpart?Amended 2018-07-02

Amendment history

Dates on which eCFR records a change to any section of Subpart JJJJJJ, newest first.

  • 2018-07-02
  • 2016-12-22

To read the rulemakings behind these dates, search the Federal Register for Subpart JJJJJJ. New EPA air rules and proposals also appear in the Federal Air Rule Tracker.

AirPermitHub provides educational, engineering, research, and compliance-support information. Information provided by the platform does not constitute legal advice and should not replace review of applicable regulations, permits, agency guidance, or consultation with qualified professionals. Full disclaimer