VA · EPA Region 3
Virginia Air Permits
Major NSR (PSD & nonattainment)
Prevention of Significant Deterioration (PSD)
PSDNew major sources and major modifications in attainment areas. Requires BACT and air quality analysis; review up to 12 months with at least one public hearing.
Thresholds (summarized from source, not a quotation)
250 tpy of any regulated pollutant, or 100 tpy for the 28 listed categories, or 100,000 tpy CO2e (restated from DEQ's Air Permits page).
9VAC5-80 Article 8; 9VAC5-85 Part IIIOfficial pageNonattainment NSR
Nonattainment NSRMajor sources in nonattainment areas; requires LAER and offsets.
Thresholds (summarized from source, not a quotation)
Northern Virginia Ozone Nonattainment Area (Ozone Transport Region): 100 tpy NOx and/or 50 tpy VOC (restated).
9VAC5-80 Article 9 (9VAC5-80-2010)Official page
Title V operating permits
Title V Operating Permit
Title VRequired for facilities above major source thresholds in 9VAC5-80-60 and certain HAP area sources. Form 805; 5-year maximum term; completeness review 60 days; processing 18 months. Title IV acid rain permits also use Form 805.
9VAC5-80 Article 1 (9VAC5-80-50 et seq.)Official page
Oil & Gas
DEQ's air permit pages list no oil and gas specific air permit. Natural gas compressor stations and similar sources use the exemption, minor NSR, SOP, and Title V framework above.
State air regulations
- 9VAC5-80Permits for Stationary Sources
- 9VAC5-80-1105Permit exemptions (minor NSR)
- 9VAC5-80 Article 6Permits for New and Modified Stationary Sources
- 9VAC5-85Permits for Stationary Sources of Pollutants Subject to Regulation (PSD for GHGs)
Forms
Guidance
Compliance
State compliance obligations (reporting, emissions inventory, testing) are being indexed. Use the Compliance dashboard preview to see how they will be tracked.
Sources
Editorial note: Exemption thresholds restated from the 9VAC5-80-1105 text (one heat input phrase quoted verbatim). Article 8 start section is cited inconsistently in the regulation definitions (9VAC5-80-1605 vs -1700). DEQ guidance APG-576 sets presumptive BACT for data center diesel gen-sets for applications on or after July 1, 2026. Applicability questions: (804) 664-3464.
AirPermitHub provides educational, engineering, research, and compliance-support information. Information provided by the platform does not constitute legal advice and should not replace review of applicable regulations, permits, agency guidance, or consultation with qualified professionals. Full disclaimer