North Dakota Air Permits

North Dakota uses a two-step system: a Permit to Construct (PTC) before building or modifying a source in a designated category (NDAC 33.1-15-14), then a Permit to Operate (PTO) issued after DEQ inspects the facility. Sources are classed as true minor, synthetic minor (federally enforceable limits), Title V major, and PSD major. North Dakota is in attainment for all criteria pollutants, so major preconstruction review is PSD. Oil and gas production facilities use a General Permit (GP-OG) filed through CERIS-ND. Applications and reports are filed electronically through CERIS-ND. Indian country is outside the GP-OG and NDDEQ's jurisdiction.
Verified against agency sourceLast reviewed 2026-10-25

Air permits & authorizations

  • Exempt sources

    Exemption

    Sources exempt from a PTC are listed in NDAC 33.1-15-14-02.13. For some minor-impact sources, an applicant may file and DEQ will decide in writing whether a permit is needed.

    NDAC 33.1-15-14-02.13Official page
  • Minor Source Permit to Construct and Permit to Operate

    Minor NSR

    PTC required before construction or modification; PTO issued after inspection confirms the facility was built per the PTC. Notify DEQ within 30 days of initial operation. A PTC lapses if construction does not start within 18 months unless extended. True minors generally do not need public comment.

    Quoted verbatim from the agency source
    less than 100 ton/yr of a criteria pollutant, less than 10 ton/yr of any single hazardous air pollutant, less than 25 ton/yr of any combination of hazardous air pollutants
    NDAC 33.1-15-14Official page
  • Synthetic Minor PTC and PTO

    State Operating

    For sources whose potential emissions are at or above major levels that accept federally enforceable limits to stay below them. Initial synthetic minor PTCs require a 30-day public comment period.

    NDAC 33.1-15-14Official page
  • Oil and Gas General Permit (GP-OG)

    General Permit

    General permit for oil and gas production facilities outside Indian country, filed through CERIS-ND. See the Oil and Gas section.

    Thresholds (summarized from source, not a quotation)

    Facility-wide criteria pollutant PTE below 250 tpy, excluding fugitives (restated from DEQ).

Major NSR (PSD & nonattainment)

  • Prevention of Significant Deterioration (PSD) Permit to Construct

    PSD

    For new major sources and major modifications (all of ND is attainment/unclassifiable). Requires BACT, air quality analysis, additional impacts analysis, and a 30-day public comment period.

    Thresholds (summarized from source, not a quotation)

    100 tons/yr for the listed source categories and 250 tons/yr for other sources, criteria pollutants only (restated from the DEQ permitting page).

    NDAC 33.1-15-15; 40 CFR 52.21(b)Official page

Title V operating permits

  • Title V Permit to Operate

    Title V

    Major source operating permit, also required for some sources due to PSD applicability or Title IV Acid Rain. Initial issuance, renewals, and significant modifications need 30-day public comment, 45-day EPA review, and affected state review where applicable.

    Thresholds (summarized from source, not a quotation)

    At or above 100 tons/yr of a criteria pollutant, 25 tons/yr combined HAP, or 10 tons/yr of a single HAP (restated from the DEQ permitting page table).

    NDAC 33.1-15-14-06Official page

Oil & Gas

North Dakota (Bakken) has a dedicated oil and gas air program. Upstream operators submit the GP-OG Application / Well Registration through CERIS-ND before well completion, then a startup notification and a Potential to Emit (PTE) report. The GP-OG is a synthetic minor permit that keeps facilities below PSD. Storage tank control is under NDAC 33.1-15-07-02.1; flares must meet NDAC 33.1-15-07-02, 33.1-15-03-03.1, 33.1-15-20, and 40 CFR 60.18. DEQ implements NSPS OOOO/OOOOa reporting. Flared gas volumes are regulated separately by the ND Industrial Commission.

  • Air Oil & Gas General Permit Application / Well Registration (GP-OG)

    General Permit

    Required for new and modified production facilities and new or recompleted wells. Startup of production notification is due within 30 days (measured from the final well), and the facility PTE Report within 90 days of startup. Sweetening units need site-specific permits.

    Quoted verbatim from the agency source
    No later than two days prior to any planned well completion activities.

    Thresholds (summarized from source, not a quotation)

    Facility-wide criteria pollutant PTE below 250 tpy, excluding fugitives (restated from DEQ).

    NDAC 33.1-15-14; GP-OG guidance effective July 1, 2025Official page
  • Well site and tank controls

    Other

    DEQ's Oil & Gas pages require new wells to have at least a pit flare on first production, and higher-emitting tanks need more efficient controls operating within 60 days of first production. Flares need an automatic igniter or continuous pilot.

    Thresholds (summarized from source, not a quotation)

    Pit flare with 90% destruction and removal efficiency; tanks emitting more than 20 tpy VOC need more efficient controls (restated from DEQ).

    NDAC 33.1-15-07-02; 33.1-15-07-02.1; 33.1-15-20Official page
  • Title V and PSD triggers for production facilities

    Other

    Facilities must notify DEQ within 60 days of exceeding Title V thresholds and apply within 12 months; PSD exceedance notification is due the first business day after the exceedance is determined.

Oil & Gas industry hub

State air regulations

Forms

Guidance

Compliance

State compliance obligations (reporting, emissions inventory, testing) are being indexed. Use the Compliance dashboard preview to see how they will be tracked.

Sources

Editorial note: The DEQ construction page phrases the synthetic minor HAP trigger as '10 ton/yr or greater of any hazardous air pollutant'; thresholds otherwise restated from DEQ's permitting table. Chapter titles (incl. PSD at 33.1-15-15) confirmed from the NDAC Article 33.1-15 index. Indian country (e.g., Fort Berthold) is under EPA Region 8 permitting (not verified on an EPA page in this review). Permitting: 701-328-5188.

AirPermitHub provides educational, engineering, research, and compliance-support information. Information provided by the platform does not constitute legal advice and should not replace review of applicable regulations, permits, agency guidance, or consultation with qualified professionals. Full disclaimer